Noise survey for Oil & Gas compressor station

Project:
Noise mitigation for a Gas Processing and Compression Plant in Texas.

Technical Information:
The noise target for this project was 45 dBA at the nearest residence to the plant.

Noise sources included:

  • Caterpillar model 3608, 3612 and 3616 engines driving Ariel four and six barrel centrifugal compressors
  • Gas coolers associated with each compressor
  • Secondary noise sources: 
    • turbo sdexpanders
    • pumps
    • fans
    • valves

 

ghui

Scope of Work:
At a stage where 30% of the total plant was installed and operational ATCO was asked to conduct a noise investigation into emissions from the gas plant, both at present and in the future, and recommend cost effective noise control measures to mitigate concerns from local residents.

The scope of work on this project included the following key tasks:

  • Long-term ambient noise survey (7 days) at the plant boundary and nearest sensitive receiver to gauge the effect of atmospheric variations and other intermittent noise sources in the local area
  • Detailed near field noise surveys to identify the noise contribution from plant components
  • Sound power levels calculations and computer-based noise modeling (Cadna/A)
  • Recommend noise control measures which would address concerns of local residents
  • Noise control design was taken through to full detailing

Fitting suitable noise control measures into an already very compact equipment layout was the major challenge on this project.  An acoustically lined building was the main component of the noise control solution, and finding suitable locations for building foundations and actually installing them wacfghs the largest of those hurdles.  The erected building steelwork shown in the figure below is testament to that hurdle being overcome.

The final stage of this project involves site verification of the plant noise emissions after installation of all noise control measures, scheduled to occur in February 2008.

As at the first quarter of 2008, the noise control project is entering the final stages of construction.

 

 