Acoustical consulting projects for power plants

Project:
Noise control study and noise abatement design for a gas-fired power plant expansion located in close proximity to residential properties in Eastern Canada.

ATCO recommended establishing a stringent noise reduction target for noise emission from the turbines to make them less dominant in the acoustic environment and to reduce their low-frequency noise emission.

 A combination of treatments including a noise barrier wall, highly acoustic rollup doors, and building ventilation silencers were installed to achieve the necessary reduction required to meet regulatory noise levels.

Recommendations for reducing community annoyance due to noise from the new units have been made. These noise reduction recommendations included establishing a stringent noise reduction target for noise emissions from the turbines to make them less dominant in the acoustic environment and to reduce their low-frequency noise emission. 

Noise survey done at thermal generating facility

Scope of Work:
Initially ATCO was retained to conduct a noise control study for the installation of two simple cycle 50MW gas turbine generators at the Tufts Cove facility.  The study showed that the most cost effective means to meet the required regulatory noise levels for the project was to retrofit the existing 350MW thermal generating plant to allow for noise contribution from the new units.

A combination of treatments including, a noise barrier wall, highly acoustic rollup doors, and building ventilation silencers were installed to achieve the reduction required to meet regulatory noise levels.

Following the installation of the second 50MW turbine generator, nearby residents expressed dissatisfaction with environmental noise from the Tufts Cove facility.  ATCO was retained to conduct an additional noise impact study find a means to reduce annoyance in the community due to noise.  ATCO conducted detailed analysis of the new units, long term noise monitoring in the community, and met with residents to discuss their concerns.  Although the plant was found to be marginally within it’s required noise levels several noise issues were identified.

  • The new turbine units are emitting low-frequency noise at an undesirably high level.
  • The characteristic frequency distribution of A-weighted environmental noise in the community has changed.  Residents are opposed to the characteristic sound of the new units.
  • The new units were emitting excessive noise during winter operation.

Noise survey for gas turbines

Additional noise abatement measures are planned for the turbine units and ATCO continues to aid the Client in developing a noise abatement strategy compatible with their long term plans for the facility.

Noise contour map for power plant

 

 

 

 

 

 

Technical Information:
This is a complex acoustical environment situated in an urban environment with mixed residential, commercial, and industrial land uses nearby.  Traffic noise is present on several nearby roadways as well as rail and ship noise.  Facility equipment includes:

  • Thermal generating facility consisting of three units totaling approximately 350MW
  • Two 50MW simple cycle gas turbine generators

Performance Target:
50 dBA at 800 feet at the nearest residence.

Project Challenges:
A complex acoustical environment involving many sources of environmental noise, a frequently changing marine climate, and topography involving a receptor uphill from the noise source make measurement and design for this site challenging.  Making an immediate improvement in the acoustic environment as well as incorporating the clients long term plans for the site make design challenging.  The design also addresses specific resident complaints instead of meeting general noise regulation requirements.

Status:
This project is currently ongoing.  Some noise abatement measures have been successfully installed, others are planned for the near future and as the clients site development plan proceeds.

 

 

 